Work has begun on building Lot 13, which will be located east of the artificial turf field on the southeast side of campus. (See map at right.)
When completed, the new lot will feature 485 stalls which can be used for parking by students, staff and visitors to the main campus of the University of Regina.
24
November 2011
Excavation for the Lot 13
underground tie-ins started today. If the weather holds then they
will be working on this for about 2 weeks.
This means they will be working on both sides of
University Drive South. Please slow down when driving thru the Lot
13 portion of University Drive South. There may be delays and there
will be flag persons directing traffic as needed.
Estimated Completion Date
The exact date when construction of the lot will be completed depends on the weather.
Monthly Updates
-
December til Spring delayed due to weather
-
November
-
Currently verifying tests and survey conducted in October.
-
Planned: Installation of sewer system.
-
Excavation for underground tie-ins. (sewer/electrical
etc)
-
October
-
Surveying completed.
-
Tree removal completed.
-
Completion of compaction tests.
-
Comprehensive elevation survey completed.
-
Completed verification of electrical ground grid location.
-
September
-
Construction began September 26.
|